Capital Improvements

2012-13 Capital Improvement Projects

1. June, 2012 - Initiated Recreation Advisory Committee.

2. Dec., 2012 - Acquired former YMCA now known as Lakeview Fitness Center - $1.9M.

3. January 1, 2013 - Lakeview Fitness Center officially opened.

4. January, 2013 - Installed outdoor sound system at Century Park ice rink.

5. January, 2013 - Initiated first annual Winter Festival in Century Park.

6. May, 2013 - Remodeled roof and structural elements at Lakeview Fitness Center.

7. June, 2013 - Began construction of new Park Maintenance Facility - $2.6M.

8. July, 2013 - Began interior renovations at Lakeview Fitness Center - $500K.

 